Question

A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution centre, and the associated transportation cost per tonne from factory to distribution centre are given in the Table.

D1D_1D2D_2D3D_3D4D_4Supply (tonnes/day)
F1F_1203011070600
F2F_21006010100
F3F_35080150901000
Demand (tonnes/day)7005003002001700

The initial basic feasible solution using the least-cost rule is _______ [in integer]

NAT

Min: 11200 Max: 11200

Answer: 11200