A cement company has three factories which transport cement to four distribution centres. The daily production of each factory, the demand at each distribution centre, and the associated transportation cost per tonne from factory to distribution centre are given in the Table.
Supply (tonnes/day) | |||||
---|---|---|---|---|---|
20 | 30 | 110 | 70 | 600 | |
10 | 0 | 60 | 10 | 100 | |
50 | 80 | 150 | 90 | 1000 | |
Demand (tonnes/day) | 700 | 500 | 300 | 200 | 1700 |
The initial basic feasible solution using the least-cost rule is _______ [in integer]
Min: 11200 Max: 11200
Answer: 11200