Question

For a continuous miner (CM) panel, the following data are given.

ParameterValue
Data related to CM
Dimension of a working face5.0 m (width) x 3.0 m (height)
Web depth, m0.6
Time for one web cut up to full height, min9
Data related to shuttle car
Bucket capacity of shuttle car, tonne10
Fill factor0.9
Number of cars2
Cycle time of each car (loading, travel, unloading), min6

Assume, unit weight of coal is 1.4 tonne/m³ and its swell factor is 1.2. Consider, 6 working hours per shift.

The non-working time in min, in working hours per shuttle car to dispatch all coal cut by the CM, is _____. (round off up to 2 decimals)

NAT

Min: 150 Max: 160

Answer: 155