A project network consists of the following activities
| Activity | Immediate predecessors | Duration (days) |
|---|---|---|
| A | -- | 3 |
| B | -- | 4 |
| C | A, B | 5 |
| D | B | 6 |
| E | D | 7 |
| F | C, E | 8 |
| G | D | 9 |
| H | F, G | X |
If the project completion time is 30 days, then the value of 'X', in days, is _______.
Min: 5 Max: 5
Answer: 5