A project network with the sequence of five activities is shown. The crashing costs of activities are
Activity | A | B | C | D | E |
---|---|---|---|---|---|
Duration (week) | 5 | 6 | 8 | 3 | 4 |
Crashing cost per week (lakh INR) | 4.0 | 2.5 | 2.0 | 3.0 | 4.0 |
If the project is crashed by one week, the increase in project cost, in lakh INR, is
2.0
2.5
3.0
4.0