The grade-tonnage distribution for the ultimate pit of a mine is given below.
Cu grade (%) | Cumulative million tonnes below the grade |
---|---|
0.1 | 0 |
0.4 | 15.0 |
0.5 | 17.0 |
0.6 | 18.0 |
0.7 | 19.0 |
0.9 and above | 23.0 |
The mill cut-off grade is 0.5% Cu. The annual mining capacity (ore + waste) is 4.5 million tonne and milling capacity is 1.0 million tonne. Excavation is planned in such a way that either of the mine or the mill runs at full capacity throughout. The planned life of the mine, in years, is _______ [round off to one decimal place]
Min: 6 Max: 6
Answer: 6