A rectangular development heading of dimension 3 m × 2.8 m is to be blasted with holes of 2.4 m in length. If the pull factor is 0.95 and swell factor is 1.20, the volume of blasted rock per round, in m³, is_____. (round off up to 2 decimals)
Min: 22.97 Max: 23
Answer: 22.985